Exciting Progress on the Dalyellup Multipurpose Community & Youth Centre (DMCYC) Project!

Published on Friday, 24 January 2025 at 9:06:16 AM

The much-anticipated DMCYC project reached a significant milestone in December 2024 with the awarding of the contract to Perkins. Since then, the momentum has been building, and as we step into 2025, work on this landmark development is well underway.

๐—ž๐—ฒ๐˜† ๐—ฑ๐—ฒ๐˜ƒ๐—ฒ๐—น๐—ผ๐—ฝ๐—บ๐—ฒ๐—ป๐˜๐˜€ ๐˜€๐—ผ ๐—ณ๐—ฎ๐—ฟ:
Design and Planning: Since December 2024, Perkins has been conducting a comprehensive design review and advancing shop drawing development to ensure precision and quality in every detail.

๐—ฆ๐—ถ๐˜๐—ฒ ๐—ข๐—ฐ๐—ฐ๐˜‚๐—ฝ๐—ฎ๐˜๐—ถ๐—ผ๐—ป: ๐—ข๐—ป ๐Ÿฒ ๐—๐—ฎ๐—ป๐˜‚๐—ฎ๐—ฟ๐˜† ๐Ÿฎ๐Ÿฌ๐Ÿฎ๐Ÿฑ, ๐˜๐—ต๐—ฒ ๐˜€๐—ถ๐˜๐—ฒ ๐—ผ๐—ณ๐—ณ๐—ถ๐—ฐ๐—ถ๐—ฎ๐—น๐—น๐˜† ๐—ฐ๐—ฎ๐—บ๐—ฒ ๐˜๐—ผ ๐—น๐—ถ๐—ณ๐—ฒ ๐˜„๐—ถ๐˜๐—ต:
• Installation of site fencing.
• Service location activities.
• Establishment of a fully operational site office.
• Civil works commencing, including ground leveling to prepare the site for the next stages of construction.

This progress marks an exciting chapter for the DMCYC project, showcasing Perkins’ dedication to swift mobilisation and detailed planning. Their commitment ensures this iconic structure will be delivered efficiently and to the highest standard.
Stay tuned for regular updates as the project reaches each milestone, bringing us closer to seeing this remarkable development take shape in our community.