DRAINAGE Location Project Description Project Status
Dalyellup College Drainage Basin Dalyellup Investigation (Report) – Flooding of playing field Planning Stage
Drainage Asset Register Shire wide Update asset register with all available information and make publicly available Survey pickup of drainage infrastructure in Boyanup completed and Capel commenced
Shire of Capel Drainage Strategy Boyanup Boyanup LWMS to support Drainage Strategy Completed
Jilley Road Gelorup Replace Existing Culvert + Headwalls Completed
Gavin’s Road Capel Replace Existing Culvert + Headwalls Completed
Weld Road Capel River Replace Existing Culvert + Headwalls Completed
Weld Road Capel River Replace Existing Culvert + Headwalls Completed
Roe Road Capel Correction of ponding to the pram ramp adjacent to Capelberry. Completed
Frances Road Gelorup Extend culvert south 4.5m to allow for footpath construction. Relocate adjacent headwall and backfill verge. Completed
Hasties Rd Drain reserve             TPS 3 outstanding works 2f Gelorup Reshape the open channel from Hasties Rd to Five Mile Brook to provide a long term manageable cross-section for the main flow path of water from catchments A and B. Survey completed
Reshape Lake McNish                   TPS 3 outstanding works 2h Gelorup Confirm volume and reshape detention basin north of Hasties Rd Survey completed
Open Drain west of Jules Rd between R 29470 and R 45489 Gelorup Undertake survey and implement works to reinstate shallow drain through reserve and BCGS land to alleviate flooding of Lot 115 Strachan Crt Completed

 

PUBLIC OPEN SPACE & LAND Location Project Description Project Status
Capel Rec Ground – Remediation Capel Part 1 – SCMP to be completed (MC)
Part 2 – Site remediation (SF) – carry over to 18/19
Planning Stage
Wonil Crescent Dalyellup Upgrade to playground equipment Completed
Central Lakes – Senior playground Dalyellup Upgrade to playground equipment Completed
Ferndale Park Dalyellup Install new shade sail Awaiting quotes & funding grant
Boyanup Recreation Ground Area Exercise Equipment Boyanup Upgrade to exercise equipment Completed
Capel Civic Precinct – Stage 3 Capel Construction & Delivery of Capel Civic Precinct Stage 3 Completed
Capel Civic Precinct – Stage 3A Capel Construction & Delivery of Capel Civic Precinct Stage 3A car park Completed
Shire Entry signs x 3 Picton. Boyanup Rd.
Tuart Drive.
Goodwood Road.
Install 3 x new Shire Entry signs Completed
Town Entry Statement Spurr Road, Capel Install new Town Entry Statement Completed
Lions Park shelter & BBQ Boyanup Install new shelter, BBQ, pad, fence and relocate existing bench Completed
Native Garden Capel Cemetery Introduce low maintenance garden Planning Stage & correct planting season
Fettlers Park Master Plan – Design Boyanup Detailed Design of Fettlers Park Development Project deferred
Age Friendly Seating Shire wide Seating Completed
Capel Cemetery Capel Signage, kerb and road repairs Installation of signs
Peppermint Grove Beach fencing Peppermint Grove Beach Fencing Contract awarded/installation due
Shire wide – POS signage, seats, shelters, bins Shire wide POS signage, seats, shelters, bins Installation of boundary signage
Galvanized Leaves- Public Art Capel Install Tuart leaves Sculpture with lighting Planning

 

PATHS Location Project Description Project Status
Bussell Highway Dual Use Path (Phase 3)  Dalyellup/      Gelorup Design and Construction 2.5m wide concrete path Contract awarded – construction  – Start May
Pedestrian Ramp Improvements Dalyellup Various new pedestrian ramps, in response to customer requests On hold
South West Hwy Boyanup replace existing asphalt path Completed
South West Hwy Boyanup replace existing asphalt path Completed
South Western Hwy – Railway Xing Boyanup MRWA liaison
West Rd Capel Construct 2.1m wide concrete path Completed

 

ROADS Location Project Description Project Status
Boundary Road Boyanup 2nd coat seal (10mm) Completed
Elgin Road Elgin Reconstruct; 6.2m seal + 0.9m shoulders Completed
Elgin Road Elgin 2nd coat seal (10mm) Completed
Ludlow North Road Ludlow Improve and widen intersection (Stirling Road) Sealing May 2019
Clarke Road Elgin Reseal to 4.0m Completed
Clarke Road Elgin Reseal to 6.2m Completed
Clarke Road Elgin Reseal to 4.0m Completed
Hurst Road Boyanup Plane and asphalt overlay Completed
Kilpatrick Road North Boyanup Gravel resheet Completed
Fowler Road Boyanup Gravel resheet Completed
Hansen Road Stratham Gravel resheet Completed
Hansen Road Stratham Clearing, realignment and gravel sheeting Tree pruning
Brookdale Road Boyanup Widen formation to 9.0m, improve drainage, clear verges Completed
Simmons Street Boyanup Plane and asphalt overlay Completed
Properjohn Road Capel Reseal to 7.0m Completed
Jules Road North Gelorup Widen formation to 9.0m – Design and preconstruction Design in Progress
Kent Road Stratham Cul-de-sac; repair pavement, install edge kerb, asphalt overlay Completed
Child Place Stratham Cul-de-sac; repair pavement, install edge kerb, asphalt overlay Completed
Ducane Road Gelorup Reseal at 6.2m (10mm) Completed
Calinup Road Stratham Design for Reconstruction – Shoulder Slumping Completed
Boyanup Road West Boyanup Realign & widen intersection Completed
Boyanup Road West Boyanup Realign and widen intersection (Elgin Road) – 2nd coat seal Completed
Boyanup Road West Boyanup Final Design, Staging & Schedule Preparation Commenced and further planning
Dalyellup Bvd Dalyellup Asphalt overlay and kerb repairs Completed
Dalyellup Bvd Dalyellup Asphalt overlay and kerb repairs Completed
Norton Promenade – Left Dalyellup Asphalt overlay and kerb repairs Completed
Norton Promenade (1510) Dalyellup Asphalt overlay and kerb repairs Completed
Norton Promenade – Right Dalyellup Asphalt overlay and kerb repairs Completed
Parade Road – Left Dalyellup Pavement rehabilitation and asphalt resurfacing (Murtin Road) Completed
Parade Road – Right Dalyellup Pavement rehabilitation and asphalt resurfacing (Murtin Road) Completed

 

BUILDINGS Location Project Description Project Status
Boyanup POS Recreation Facilities Boyanup Upgrade Bowling Club Sports Pavilion + facilities Football & basketball completed, Bowling club in progress
Jamison Footbridge Capel Upgrade Tender doc in progress
Timber Structures -2 Shire wide North Beach Access Stairway Dalyellup Beach Completed
Timber Structures -3 Shire wide Dalyellup Timber Structures – lake link ramp Completed
Roof Access Anchor Points Shire wide Upgrade Completed

 

BRIDGES Location Project Description Project Status
Bentley Road Bridge Ludlow Waterways analysis Completed
Dardanup West Road Bridge Dardanup Includes approach road of DW Rd In progress – MRWA

Parks and Garden Schedule

Please see below a schedule of annual planned works within the Shire. This schedule is subject to change due to weather conditions, emergencies and other operational factors. Please click on the image below for a larger view.

Works Schedule

Please see below a schedule of annual planned works within the Shire. This schedule is subject to change due to weather conditions, emergencies and other operational factors. Please click on the image below for a larger view.

Long Term Program of Works

Program of Works – Paths (2019 – 2026) 

Program of Works – Roads (2019 – 2029)

Program of Works – Drainage (2019-2023)

Bushland Reserve Asset Management Plan PoW (2019-2029)